Renewal of Drinking Water Pipeline in Unterlangenegg BE
Bachgrabe, 3614 Unterlangenegg
Get new building permits filed in Unterlangenegg by e-mail
For professionalspro
The project covers the renovation and extension of the drinking water and fire hydrant pipeline in Unterlangenegg, with a partly revised route and a crossing under a watercourse by horizontal drilling. For civil engineering and earthworks companies, this means pipe laying work, including the drilled crossing under the watercourse; the application has been submitted but not yet approved.
Trades involved
Summary written by NovaNest’s AI from the official notice; check the details in the file.
The project
Project change: partially modified pipeline route, now with watercourse crossing by horizontal directional drilling (jetting method), for rehabilitation and extension of the drinking water and hydrant line
Automatic translation of the official notice published in French.
Progress
Filed on 18 November 2026 · status as of 18 November 2026
- 1Filed
- 2Review
- 3Final review
- 4Decision
- 5Construction
- 6Closed
People involved
Other projects nearby
Grabenstrasse Renovation and Utility Networks in Steffisburg BESteffisburg · BE · 30.09.2026
Villa and Annex Dwelling in Oberhofen am Thunersee BEOberhofen am Thunersee · BE · 07.10.2026
Façade Renovation in Eggiwil BEEggiwil · BE · 28.10.2026
Wood Heating Replaced by Pellet System in Eggiwil BEEggiwil · BE · 30.09.2026
Reconstruction of Barns and Storage Rooms in Zäziwil BEZäziwil · BE · 21.10.2026
Oil Heating Replaced by Pellet Heating in Eggiwil BEEggiwil · BE · 11.11.2026
Information from the official public-inquiry notices. It may be incomplete; the official file prevails.